YEKA GES-2026 Solar Power Auctions Conclude

Total of €31.585 million in contribution payments pledged in the auctions
3 November 2026

The capacity allocation auctions for solar energy investments under the Renewable Energy Resource Area (YEKA) model, held for the sixth time this year, have concluded.

A total of 19 legal entities participated in the YEKA GES-2026 auctions for 785 Megawatts of capacity across 11 areas, with nine securing capacity allocation rights.

Egesa Elektrik İnşaat Enerji Üretim A.Ş. secured the largest share of capacity, winning a total of 345 Megawatts across three projects.

The most competitive bidding took place for the G26-Malatya solar power project, which Ezel Mensucat San. ve Tic. A.Ş. won after 16 rounds with a contribution payment commitment of €91,000 per Megawatt, totaling €5.005 million.

The total contribution payments pledged in the YEKA GES-2026 auctions amounted to €31.585 million, excluding value-added tax.

The auction results were as follows:

  • G26-Denizli GES: Temmuz Güneş Denizli Enerji Üretim San. ve Tic. A.Ş. won the auction for 30 Megawatts of capacity with an electricity purchase price bid of 3.25 euro cents per Kilowatt-hour and a contribution payment commitment of €60,000 per Megawatt, totaling €1.8 million, submitted in the seventh round.
  • G26-Ankara-1 GES: Erser Grup Tarım Ürünleri San. ve Tic. A.Ş. won the auction for 40 Megawatts of capacity with an electricity purchase price bid of 3.25 euro cents per Kilowatt-hour and a contribution payment commitment of €22,000 per Megawatt, totaling €880,000, submitted in the third round.
  • G26-Ankara-2 GES: İklim İnvest Enerji ve Teknoloji Yatırımları A.Ş. won the auction for 30 Megawatts of capacity with an electricity purchase price bid of 3.25 euro cents per Kilowatt-hour and a contribution payment commitment of €12,000 per Megawatt, totaling €360,000, submitted in the first round.
  • G26-Konya GES: İş Enerji Yatırımları A.Ş. won the auction for 110 Megawatts of capacity with an electricity purchase price bid of 3.25 euro cents per Kilowatt-hour, following an initial sealed financial bid of 3.28 euro cents per Kilowatt-hour, and a contribution payment commitment of €64,000 per Megawatt, totaling €7.04 million, submitted in the seventh round.
  • G26-Kahramanmaraş-2 GES: Temmuz Güneş Kahramanmaraş Enerji Üretim San. ve Tic. A.Ş. won the auction for 85 Megawatts of capacity with an electricity purchase price bid of 3.25 euro cents per Kilowatt-hour and a contribution payment commitment of €60,000 per Megawatt, totaling €5.1 million, submitted in the eighth round.
  • G26-Kahramanmaraş-3 GES: Temmuz Güneş Kahramanmaraş Enerji Üretim San. ve Tic. A.Ş. won the auction for 50 Megawatts of capacity with an electricity purchase price bid of 3.25 euro cents per Kilowatt-hour and a contribution payment commitment of €74,000 per Megawatt, totaling €3.74 million, submitted in the 11th round.
  • G26-Malatya-1 GES: Ezel Mensucat San. ve Tic. A.Ş. won the auction for 55 Megawatts of capacity with an electricity purchase price bid of 3.25 euro cents per Kilowatt-hour, following an initial sealed financial bid of 3.84 euro cents per Kilowatt-hour, and a contribution payment commitment of €91,000 per Megawatt, totaling €5.005 million, submitted in the 16th round.
  • G26-Diyarbakır GES: Egesa Elektrik İnşaat Enerji Üretim A.Ş. won the auction for 200 Megawatts of capacity with an electricity purchase price bid of 3.25 euro cents per Kilowatt-hour, following an initial sealed financial bid of 3.85 euro cents per Kilowatt-hour, and a contribution payment commitment of €16,000 per Megawatt, totaling €3.2 million, submitted in the second round.
  • G26-Mardin-2 GES: Egesa Elektrik İnşaat Enerji Üretim A.Ş. won the auction for 120 Megawatts of capacity with an electricity purchase price bid of 3.25 euro cents per Kilowatt-hour and a contribution payment commitment of €18,000 per Megawatt, totaling €2.16 million, submitted in the third round.
  • G26-Batman GES: Egesa Elektrik İnşaat Enerji Üretim A.Ş. won the auction for 25 Megawatts of capacity with an electricity purchase price bid of 3.21 euro cents per Kilowatt-hour, following an initial sealed financial bid of 3.85 euro cents per Kilowatt-hour, and a contribution payment commitment of €36,000 per Megawatt, totaling €900,000, submitted in the sixth round.
  • G26-Elazığ GES: Ecogreen Elektrik Enerji Üretim A.Ş. won the auction for 40 Megawatts of capacity with an electricity purchase price bid of 3.25 euro cents per Kilowatt-hour and a contribution payment commitment of €36,000 per Megawatt, totaling €1.44 million, submitted in the seventh round.